R. 21-10-002
Track 3B.1 includes Incentives for LSE’s deficient in year-ahead RA filings and refinements to the MCC buckets adopted in D. 20-06-031.
Comments on Track 3B.1 Proposals:
SDG&E:
- Proposes that energy storage resources be qualified as MCC Bucket 3 (not MCC 1) given the capability of these resources to charge and discharge throughout the day
- Further refinement of MCC buckets needed to ensure consistency with the modified RA framework adopted by the Commission.
CAISO submitted four Track 3B.1 Proposals:
- Resource Adequacy Import Requirements
- Effective Load Carrying Capability Methodology for Variable-Output Demand Response
- Availability Limited Resource Procurement
- Increased PRM for 2022